Pantopia Theater Additions and Renovations
Busch Gardens Tampa
The Pantopia Theater project was a part of the Pantopia Realm expansion project. The scope of this project included the renovation and re-theming of the existing 4D-theater building, a new addition for animal holding, new exterior covered animal holding areas, and a new off-site animal and night house area. A major part of the scope was the gutting and removal of the entire seating area, including all slabs, in order to re-configure the theater seating to meet current accessibility requirements. Meyer Associates provided conceptual design, architecture, and engineering services for the project.